ENERGY & BUILDING-CODE COMPLIANCE · CASE STUDY

San Francisco Office Energy & Compliance — Inputs

NOT COMPLIANT / NOT ACCEPTED — native Title 24 runs rejected; official report not generated; ASHRAE PRM blocked

Inputs

Building and site

Building
Synthetic WF1 London Run 4 office, single storey, 12 rooms; geometry unchanged (same geometry hash in London and SF)
Areas
756 m² conditioned (8,137.52 ft²); 864 m² in the model incl. 108 m² unconditioned plantroom
Site
Hypothetical San Francisco site, provisional ZIP 94103; permit date assumed 2026-11-02
Weather (offline)
CEC CZ2022 climate-zone 3 file, Oakland station 724930 — named only, not shipped (licence not stated)
Weather (native Title 24)
CZ2025 Oakland file locked by the Title 24 mode (D-CX-21)
Lighting
WF1 design 9,864 W installed; Title 24 area-category allowance 5,480 W

CEC construction mapping (native U-values, W/m²K)

ConstructionWF1 UCEC-mapped UChange
External wall0.26130.2605−0.3 %
Roof0.18010.1782−1.1 %
Exposed floor0.22090.2223+0.6 %
Partition1.85681.8076−2.6 %

Title 24 accepts only CEC library materials; the WF1 layers were mapped with insulation R preserved (D-CX-22, engineer review required). Glazing data are European values, not certified US ratings.

Sanitised derivative of preserved evidence (compliance-* evidence folders, branch feat/compliance-engine). Nothing was re-simulated for this pack; IESVE was not started. Screenshots are cropped and reviewed; plots and the report contain only values read from the evidence. Not a compliance document. · Pack sf-office-compliance-r2 (built 2026-10-25); every file is checked against its SHA-256 before it is shown.